Dundashill Plot 3, Glasgow
Dundashill is a Transformational Regeneration Area located north of Glasgow’s city centre that is currently being extensively re-developed to deliver 600 low-carbon, energy-efficient homes.
Plot 3 is presently being delivered by CCG (Scotland) Ltd on behalf of West of Scotland Housing Association and it is set to become Scotland’s largest Passivhaus residential development with the creation of 90 homes for mid-market rent.
Passivhaus homes are so well constructed, insulated and ventilated that they retain heat from the sun and the activities of their occupants, requiring very little additional heating or cooling, and are seen as key to tackling fuel poverty with a reduction in energy costs of around 90% on baseline building standards.
Arc-Tech MU is supporting this innovative project with a duel-fuel Services package comprising:
Water
- 2no water connections from existing 180mm services with the installation of 411m of 125/90/63mm BARRIER pipework
- 10No 63mm BP Water services shall be installed to serve each of the properties, terminating at a boundary box
- 3No Test & Chlorination of the new water mains
Electrical
- 2no EAN LV mains cables connections with 430m of LV mains cabling installed
- 10no MSDB’s shall be installed within the ground floor of each stairwell.
- New mains to serve communal supply (3-phase 400A), 1No sprinkler tank (3-phase) and 2no Street lighting control pillars (1-phase)
Client:
West of Scotland Housing Association